Roadwork on Prescott East Highway Starts 10/10 Featured

David McAtee October 02, 2022 863

Prescott East Highway Reconstruction Project

Big Idea

  • Roadwork will begin on Prescott East Highway on October 10, expected completion in January 2023
  • Turn lanes, drainage improvements, sidewalks and new asphalt
  • Some asphalt will be completely replaced
  • Expect closures, detours, lane restrictions and diversions, speed reductions and flaggers
  • Read more...

 

Be prepared for roadwork on Prescott East Highway

Asphalt Paving & Supply, Inc., in conjunction with Yavapai County and the Town of Prescott Valley, will be performing roadwork on Prescott East Highway from the intersection with Highway 69 through Antelope Lane. Construction will begin October 10, 2022, continuing through January 26, 2023. Road construction will be performed in three phases.

Phase one work will be from Highway 69 to Copper Hill Road and will consist of concrete sidewalk improvements, the addition of a turn lane, drainage improvements and placement of new asphalt. Work completed in phase 1 will impact drivers accessing Prescott East Highway but will always remain open. 

Phase two work will be from Copper Hill Road to Sunset Lane and will consist of full depth recycling of the asphalt, cement treatment of base material, paving, and reestablishment of the concrete curb for the median. Mini traffic circles will be added to assist traffic in the neighborhood. Phase two construction will close Prescott East Highway to through traffic, detours will be clearly marked, and intersections will remain open with minimal traffic control for traffic flowing around the work zone.

Phase three construction will be from Sunset Lane to Antelope Lane and will consist of full depth recycling of the asphalt, cement treatment of base material, paving, and reestablishment of the concrete curb at the median. Mini traffic circles will be added to assist traffic in the neighborhood. Phase three construction will close Prescott East Highway to through traffic, detours will be clearly marked, and intersections will remain open with minimal traffic control for traffic flowing around the work zone

During critical periods of construction portions of Prescott East Highway will be closed to through traffic, detour routes will be signed, however, motorists may encounter lane restrictions, lane diversions, reduced speeds, and flagging operations at the intersections with Prescott East Highway and the detour routes. Motorists should expect detours, minor delays and allow extra time to get through the construction area. Please follow all traffic control devices when travelling through the work zone.

For additional information, please contact Yavapai County Public Works at 928-771-3183 or visit us on the web at www.yavapaiaz.gov/publicworks.

 